The following parts are installed onto the Sideskin Roof Outer:
Bodyside Outer LH & RH
Upper Sleeper Front Member
B-Dent Side Panel (Option Only)
Side Upper Roof Panel LH & RH (Day Cab)
L230 Short
Pin Guide Assemblies
After all parts are installed, the Sideskin will be sent to 2V01 Framing and 2V10 Bodyside RH
via the Overhead Conveyor.
Use the searchable fields in the table below to view, select, and download the desired documentation.
The documentation that can be found in the table below includes
VMMS Sheets, Lubrication Maps, and Standard Maintenance Procedures
(SMPs).
Roll over to view components2V08 Sideskin Roof Outer Equipment Layout
Process
The following is a abridged version of the sequence of operation for the 2V08 Sideskin Roof Outer Cell.
Select the Download button for the full sequence of operation.
Operator places parts from bins and totes onto the Geo Fixture (2V08-V01WR1).
2
Robot (2V08-V01AR201) makes multiple welds to the LH Side Skin and then moves to clear.
3
Robot (2V08-V01AR201) obtains the LH Side Skin from the Geo Fixture (2V08-V01WR1).
4
The Turntable (2V08-V01WR1) rotates 180 degrees.
5
Simultaneously, as Robot (2V08-V01AR201) completes its process, Robot (2V08-V02AR11) picks
a Roof Panel from the Fixture Rack (2V08V01Cl1) and places it in the Buffer Racks
(2V08-V01CM3 or 2V08-V01CM4).
6
Power and Free Transfer (2V08-V01GL19) transfers in for the LH Side Skin.
7
Robot (2V08-V01AR211) picks LH Side Skin from the Geo Fixture (2V08-V02WR1UQ52).
8
Robot (2V08-V01AR211) moves to data scribe and date is scribed to LH Side Skin.
9
Robot (2V08-V01AR211) places cut LH Side Skin in Power and Free Transfer (2V08-V01GL19).
10
Power and Free Transfer (2V08-V01GL19) transfers out with LH Side Skin.
11
Robot (2V08-V01AR201) makes multiple welds to the RH Side Skin and then moves to clear.
12
Robot (2V08-V01AR201) obtains the RH Side Skin from the Geo Fixture (2V08-V01WR1).
13
Robot (2V08-V01AR211) picks RH Side Skin from the Robot (2V08-V01AR201).
14
Robot (2V08-V01AR211) loads uncut LH and RH Side Skin to Geo Fixture (2V08-V02WR1UQ52).
15
Robot (2V08-V01AR211) picks cut RH Side Skin from Geo Fixture (2V08-V02WR1UQ52).
16
Robot (2V08-V01AR211) moves to the date scribe (2V08-V01PF1) and date is scribed.
17
Robot (2V08-V01AR211) loads cut RH Side Skin to Power and Free Transfer (2V08-V01GL19).
18
Meanwhile, Robot (2V08-V02AR181) makes multiple laser cuts on parts on the Turntable (2V08-V02WR1).
Roll over to view components2V08 Sideskin Roof Outer Equipment Layout